The Park Avenue reconstruction project, from Canyon Springs Road to Gurley Street, will get underway after relocation of utilities and property acquisitions are completed. The updated schedule includes advertisement for bids in late February followed by street construction beginning in May, and extending to completion in 2015.
| Relocation of third-party utility lines
• APS telephone poles and transfer wires • CenturyLink and CableOne lines • Remove unnecessary telephone poles
|
Underway | 4 weeks
(February) |
| Acquisition of necessary rights-of-way and issuance of Temporary Construction Easements | Underway | 4 weeks
(February) |
| Advertisement of construction project for bids; award contract | 4 weeks | 10-11 weeks (April/May) |
| Reconstruction work – water and sewer lines, drainage, and street pavement | 10-11 weeks | 12 months
(May 2015) |